Track monitoring close to the construction site
Cautus Geo put the subway track at Fyrstikkbakken on intensive monitoring. AF Gruppen was the client. They were to build 160 apartments close to the track.
Problem statement
The go-ahead has been given to build 160 new homes close to the metro line at Fyrstikkbakken in Oslo. Prior to the start of construction, blasting was required on the site. The risk was possible damage to the subway track that could endanger life and property, or cause discomfort for travellers on the heavily trafficked subway line. Sporveien set requirements for track monitoring.
Solution
Automatically instrumented SAA sealing hose along the track. It measured continuously and sent data in real time to the Cautus Web access solution. There, tolerance limits were established for automatic notification to AF Gruppen and Sporveien.
Intensive track monitoring in Fyrstikkbakken
The purpose was to ensure the safety of Sporveien's travellers, structures and infrastructure.
Fyrstikkbakken 14 is being developed into a showcase for environmentally friendly housing. AF Gruppen is building 160 apartments in solid wood. It is FutureBiult's first commercial housing project in solid wood. The goal is a 50 per cent reduction in greenhouse gas emissions.
Sporveien carries 60,000 passengers on tracks past Fyrstikkbakken every day. There are several major building and construction projects close to the track between Bryn and Hellerud.
Customer
AF Group
Year
2021 - 2022
Location
Oslo, Norway
Application area
Technology
Instrumentation and measurements that show facts in real time help create peace of mind.
Henrik Strand, site manager at AF Gruppen.