Monitoring the external environment for the new E6 motorway
The new E6 motorway from Biri to Øyer runs through vulnerable nature. Cautus Geo monitors water quality, vibrations, noise, dust and groundwater.
Problem statement
The new E6 motorway from Biri to Øyer passes through vulnerable nature. The Lågendelta will be crossed. It is one of Norway's largest inland deltas. The motorway will come close to the important nature reserve, crossing rivers and streams. New tunnels can change the groundwater level for private water supplies, as well as causing noise, dust and vibrations that may inconvenience those who live and work along the motorway.
Solution
Cautus Geo monitors all aspects of the external environment. The first instruments were installed in the autumn of 2023. Continuous and automatic monitoring and logging of water quality, noise and vibrations has been established. Groundwater monitoring, water sampling and pore pressure will be added later. Among other things, this will secure water supplies in the area.
AF Gruppen is building a new motorway past Lillehammer. The assignment is divided into two major contracts: Roterud-Storhove in Gjøvik and Lillehammer municipality and Storhove-Øyer in Lillehammer and Øyer municipality.
The new motorway largely follows the current E6, but a new bridge will be built to cross the Lågendelta and a new tunnel will shield the residents of Fåberg from traffic and noise. In addition, 4.5 kilometres of the current E6 will be demolished. There, nature will once again take over. Among other things, this will contribute to 40 hectares of newly cultivated land.
In Øyer, there will be a new pedestrian and cycle path. The assignment also includes a wildlife fence, a new municipal water pipeline through the tunnel, and landslide and safety measures.
Cautus Geo has established a significant number of measuring stations. Data is continuously fed into Cautus Web. Everything can be read in near real time, and automatic alerts have been established if defined limit values are breached.
The state administrator has granted discharge permits under the Pollution Control Act for construction activities, tunnelling, dredging and filling in Lake Mjøsa, the construction of a new bridge over Lågen and the reuse of blasted rock from the Brøttum formation.
Much of the instrumentation carried out by Cautus Geo relates to environmental monitoring of water, Lågen and what affects Lake Mjøsa, but all of the external environment is included, including pore pressure and drinking water sources when the tunnel work starts. "The environmental monitoring for the new E6 motorway in Inland Norway is complex, wide-ranging and extends over several years.
Customer
AF Group
Year
2023 - 2030
Location
Inland
Application area
Technology
- Automatic monitoring with alerts is absolutely crucial. It's all about having control and making sure we do things correctly in accordance with permits, guidelines, regulations and the zoning plan.
Head of Environment and Quality, Morten Martinsen in AF Gruppen.
Contact person
Switchboard telephone +47 990 96 580 or e-mail salg@cautusgeo.com