Controlling noise and subsidence in Lier

Home page Projects Controlling noise and subsidence in Lier
20180913_140236

Cautus Geo is monitoring backfilling in Gilhusbukta in Drammensfjorden. New land will be established there with 4.8 million tonnes of rock mass. It will be the start of Fjordbyen.

Problem statement

In Drammensfjorden, 200 acres of new land have been established. A drainage technique has been used to reduce settlement time by 50-60 years. The goal is early development. The infill will form a district in a brand new city that can accommodate 16,000 residents in the centre of the fjord. Strict environmental requirements have been set by the Norwegian Environment Agency. This concerns both noise and life above and below water in the area, which is important for vulnerable species.

Solution

Cautus Geo installed 27 pore pressure gauges in June 2018. They were installed at nine different locations in the fjord at depths down to 50 metres below the seabed. In addition, three settlement meters were installed, each at 300 metres. This provides control of any subsidence every single metre from land and 300 metres out into the fjord. In addition, noise meters were established close to the construction area and at various reference points. More pore pressure gauges have since been drilled down to various depths in the ground, but also on the top deck of the landfill. Measurement data is analysed in real time in Cautus Web, with reference limits for automatic alerts and alarms.

The municipality of Lier is transforming an industrial area into an urban city. The plan includes the new land in Gilhusbukta. The infill is 200 acres in size. It will later be transformed into an island community. 40 acres will be dug up. The water will flow through channels. In addition, there will be public bathing areas.

The area is located between two important spawning rivers for trout and salmon, Lierelva and Drammenselva, and close to a nature reserve with red-listed bird species. The fish and bird life will benefit from the backfill. Strict environmental requirements and requirements for a new shallow water area have been set by the Directorate.

Management and documentation

Continuous and automatic monitoring will ensure the work is carried out and document the impact on the environment during the project and after everything has been completed. In addition, the area will be ready for construction in record time.

Cautus Geo is one of several organisations that have provided continuous and automatic monitoring over the years. Cautus Geo is responsible for measuring noise and settlement/tracking pressure horizontally and vertically.

The actual backfill was completed in 2022. A preload of almost two million tonnes of stone was placed on top. This corresponds to the weight of the roads, facilities and buildings planned for the new land. Before that happens, canals must be established and contaminated soil on a neighbouring site must be cleaned up.

Vertical drainage

700 kilometres of vertical drainage pipes were established before backfilling began. They run 30 metres below the seabed. This cuts the settling time by more than 50 years. Cautus Geo has documented all subsidence since before the first stone was filled in. The measurements are still ongoing.

Noise meters were also installed before the work started. This is to ensure that the work is carried out within the stipulated noise requirements from the Norwegian Environment Agency. Measurements are therefore taken close to the plant. In addition, there are several reference points in the area.

The transformation from industry to new town is anchored in Lier municipality's municipal plan from 2009. The transformation is already clearly visible with the new hospital on Brakerøya, which opened in 2025, and the new land in Gilhusbukta.

Customer

Gilhusbukta Sjøgrunn AS

Year

2018 - 2030

Location

Lier municipality

Application area

Technology

Automatic and continuous monitoring is crucial. It provides information and documentation to the environmental authorities and guarantees that construction can begin without the risk of subsidence damage. The measurements document that everything has been carried out properly and that all objectives have been achieved when the project is completed.

Project manager Wiliam Kornmo